Cook Islands: Avatiu Port Development Project

In 2007, the Government of the Cook Islands adopted a 20-year Preventive Infrastructure Master Plan (IMP), prepared under an Asian Development Bank (ADB) technical assistance, as an integral part of the National Sustainable Development Plan, 2007–2010. The IMP assessed the condition and management of existing infrastructure. It concluded that lack of investment in maintenance and rehabilitation resulted in the failure to meet existing demands, thus hindering economic development. The development of Avatiu port was identified as a high priority under the IMP due to the risk of serious deterioration and operational failure.

This report validates the completion report’s assessment of the project. IED overall assessment: Less than successful.

Asset Management for Sustainable and Improved Infrastructure Services Delivery: Technical Assistance Completion Report

Technical assistance completion reports describe for technical assistance projects the expected impact, outcome and outputs; conduct of activities; evaluation and achievement of the expected outcomes; an assessment and rating; major lessons; and recommendations and follow-up actions. This document dated August 2015 is provided for the ADB project 43422-012 in the Cook Islands.

Avatiu Port Development Project: Completion Report

Project or program completion reports evaluate design, implementation and performance of a project or program, and provide an overall assessment and recommendations.

This document dated June 2015 is provided for the ADB project 40287-013 in the Cook Islands.

HIV/AIDS Prevention and Capacity Development in the Pacific

Project or program completion reports evaluate design, implementation and performance of a project or program, and provide an overall assessment and recommendations.

This document dated December 2011 is provided for the ADB project 38599-022.

Cook Islands: Cyclone Emergency Assistance Project [Loan 2174-COO]

REPORT DETAILS: Cook Islands: Cyclone Emergency Assistance Project [Loan 2174-COO] sector: Energy, Public Sector Management, Transport, Water and Other Urban Infrastructure and Services | country: Cook Islands Lessons The project would have benefited considerably if a...

Waste Management Project

Project or program completion reports evaluate design, implementation and performance of a project or program, and provide an overall assessment and recommendations.

This document dated December 2005 is provided for the ADB project 32536-013 in the Cook Islands.

Third Cook Islands Development Bank Project

Project or program completion reports evaluate design, implementation and performance of a project or program, and provide an overall assessment and recommendations.

This document dated October 2003 is provided for the ADB project LN1380 in the Cook Islands.

Economic Restructuring Program (Loan 1466-COO[SF])

This report evaluates the performance of the Economic Restructuring Program designed to support macroeconomic stability, increased private sector participation, and mitigation of social costs in the Cooks Islands.