Select Page

Kyrgyz Republic

Latest Reports

Kyrgyz Republic: Tax Administration Reform and Modernization Project

November 23, 2015 | Public Sector Management | Validation of Project/Program Completion Report

The Tax Administration Reform and Modernization Project was one of a series of projects supported by the Asian Development Bank (ADB) in the Kyrgyz Republic to foster economic growth and public governance by increasing tax and customs revenues and improving tax administration. The project was well aligned with the government objectives outlined in the Joint Country Support Strategy to introduce modern technology in tax administration, improve operations, and reduce corruption. During project design, fiscal consolidation was considered vital to maintain the good performance of the economy and sustaining its achievements.

This report validates the completion report’s assessment of the project. IED overall assessment: Successful.

view lessons »


Investment Climate Improvement Program: Validation of Completion Report

October 20, 2015 | Finance | Validation of Project/Program Completion Report

This report validates the completion report’s assessment of the program. IED overall assessment: Successful.

view lessons »


CAREC Transport Corridor I (Bishkek-Torugart Road) Project 2: Completion Report

September 11, 2015 | Transport | Project/Program Completion Reports (PCR)

This report evaluates the design, implementation and performance of said project in Kyrgyz Republic, and provides an overall assessment and recommendations.

view lessons »


Support for Strategic Assessment of the Kyrgyz Economy to Promote Inclusive Growth: Technical Assistance Completion Report

August 1, 2015 | Public Sector Management | Technical Assistance Completion Report

Technical assistance completion reports describe for technical assistance projects the expected impact, outcome and outputs; conduct of activities; evaluation and achievement of the expected outcomes; an assessment and rating; major lessons; and recommendations and follow-up actions. This document dated August 2015 is provided for the ADB project 45414-001 in the Kyrgyz Republic.

view lessons »


Prevention and Control of HIV/AIDS and Other Communicable Diseases in Central Asia Regional Economic Cooperation Countries: Technical Assistance Completion Report

July 1, 2015 | Health, Industry and Trade | Technical Assistance Completion Report

Technical assistance completion reports describe for technical assistance projects the expected impact, outcome and outputs; conduct of activities; evaluation and achievement of the expected outcomes; an assessment and rating; major lessons; and recommendations and follow-up actions. This document dated July 2015 is provided for the ADB project 46096-001.

view lessons »


Second Community-Based Early Childhood Development: Technical Assistance Completion Report

April 1, 2015 | Transport | Technical Assistance Completion Report

Technical assistance completion reports describe for technical assistance projects the expected impact, outcome and outputs; conduct of activities; evaluation and achievement of the expected outcomes; an assessment and rating; major lessons; and recommendations and follow-up actions. This document dated April 2015 is provided for the ADB project 37430-012 in the Kyrgyz Republic.

view lessons »


Investment Climate Improvement Program: Completion Report

March 25, 2015 | Finance, Industry and Trade, Public Sector Management | Project/Program Completion Reports (PCR)

This report evaluate the design, implementation and performance of said program in Kyrgyz Republic, and provides an overall assessment and recommendations.

view lessons »


Tax Administration Reform and Modernization Project: Completion Report

March 24, 2015 | Public Sector Management | Project/Program Completion Reports (PCR)

Project or program completion reports evaluate design, implementation and performance of a project or program, and provide an overall assessment and recommendations.

This document dated March 2015 is provided for the ADB project 39015-042 in the Kyrgyz Republic.

view lessons »


Kyrgyz Republic: Community-Based Infrastructure Services Sector Project (Supplementary)

December 29, 2014 | Water and Other Urban Infrastructure and Services | Validation of Project/Program Completion Report

view lessons »


Kyrgyz Republic: Vocational Education and Skills Development Project

December 29, 2014 | Education | Validation of Project/Program Completion Report

view lessons »


Download Report

Download Excel File

Filter Reports

Report Search & Filter Main: Kyrgyz Republic
Sending