Major Bridges Study: Technical Assistance Completion Report

sector: Transport | country: Papua New Guinea

Despite the delays in the recruitments, the consultant was able to complete the assignment on time and submitted high quality report. This was mainly due to the 90:10 selection method and lump sum contract as was jointly expressed by the consultant and DOW (Department of Works). Lump sum contract enabled the consultant to work at their own pace given the flexibility in managing their resources and staging their inputs. Moreover, the consultant was actively pursuing for the feedbacks and comments on their deliverables which resulted timely payments.