The project completion report (PCR) identifies a number of useful lessons. The present validation supports them in full. These are reiterated here: (i) the project design should be in consonance with the implementation capability of the executing agency, especially when it is the first project, or the executing agency is generally inexperienced; (ii) since excessively complex projects face an exponentially rising risk of failure, this must be avoided unless the problem can only be addressed through an innovative and untried solution; and (iii) subnational operations need to be prepared and processed more cautiously and carefully since their functions and powers are derived from multiple sources with overlapping jurisdictions.