Select Page

Tajikistan

Latest Reports

Tajikistan: Khatlon Province Flood Risk Management Project

November 23, 2015 | Agriculture, Natural Resources, and Rural Development | Validation of Project/Program Completion Report

The Republic of Tajikistan has a long-standing vulnerability to natural disasters particularly floods due to its terrain and climate. It relied on flood protection facilities that degraded over the years due to insufficient operation and maintenance. The threat of flooding intensified in recent years as water flows from its upper mountains has increased. Furthermore, continued growth in both population and agricultural production in many flood-prone areas only increased the risks of physical and socioeconomic damage from flooding.

Earlier floods in 1998 and 1999 inflicted damage to the agriculture and infrastructure sectors worth $55 million and resulted in the deaths of 32 inhabitants. These catastrophic events caused the government to recognize that a holistic and coordinated approach of structural protection measures and nonstructural measures was needed to be put in place. It also underscored the need to simultaneously strengthen the institutional and legal frameworks and to upgrade the technical capacity of key flood management institutions.

This report validates the completion report’s assessment of the project which aimed to have an operational, well-maintained, effective, and sustainable flood management system. IED overall assessment: Successful.

view lessons »


Rural Development Project: Project Completion Report

September 21, 2015 | Agriculture, Natural Resources, and Rural Development, Finance, Transport | Project/Program Completion Reports (PCR)

Project or program completion reports evaluate design, implementation and performance of a project or program, and provide an overall assessment and recommendations.

This document dated September 2015 is provided for the ADB project 37530-013 in Tajikistan.

view lessons »


Strengthening Public Resource Management Program: Completion Report

September 17, 2015 | Public Sector Management | Project/Program Completion Reports (PCR)

This report evaluates the design, implementation and performance of said program in Tajikistan, and provides an overall assessment and recommendations.

view lessons »


Prevention and Control of HIV/AIDS and Other Communicable Diseases in Central Asia Regional Economic Cooperation Countries: Technical Assistance Completion Report

July 1, 2015 | Health, Industry and Trade | Technical Assistance Completion Report

Technical assistance completion reports describe for technical assistance projects the expected impact, outcome and outputs; conduct of activities; evaluation and achievement of the expected outcomes; an assessment and rating; major lessons; and recommendations and follow-up actions. This document dated July 2015 is provided for the ADB project 46096-001.

view lessons »


Khatlon Province Flood Risk Management Project: Completion Report

April 15, 2015 | Agriculture, Natural Resources, and Rural Development | Project/Program Completion Reports (PCR)

Project or program completion reports evaluate design, implementation and performance of a project or program, and provide an overall assessment and recommendations.

This document dated April 2015 is provided for the ADB project 40046-013 in Tajikistan.

view lessons »


Sustainable Cotton Subsector Project: Validation of Completion Report

January 16, 2015 | Agriculture, Natural Resources, and Rural Development, Finance | Validation of Project/Program Completion Report

This report validates the completion report’s assessment of the project. IED overall assessment: Less than successful.

view lessons »


Tajikistan: Dushanbe-Kyrgyz Border Road Rehabilitation Project, Phase II

December 22, 2014 | Transport | Validation of Project/Program Completion Report

During project preparation, more than 70% of the roads in Tajikistan were considered to be in poor condition. The road sections needing rehabilitation created bottlenecks that obstructed trade between much of Afghanistan, the People’s Republic of China (PRC), the Kyrgyz Republic, and Tajikistan. Improvements in these road sections were expected to facilitate regional trade, provide better connections, and enable the smooth transport of the area’s agricultural products to the Dushanbe and regional markets.

view lessons »


Afghanistan and Tajikistan: Regional Power Transmission Interconnection Project

November 25, 2014 | Energy | Validation of Project/Program Completion Report

This report validates the completion report’s assessment of the project, which aimed to enhance regional cooperation in the power sector through transmission interconnectivity. IED overall assessment: Successful.

view lessons »


Tajikistan: Agriculture Rehabilitation Project

November 18, 2014 | Agriculture, Natural Resources, and Rural Development | Project/Program Performance Evaluation Report (PPER)

This performance evaluation report assesses the performance and impact of the program and generates a series of findings, lessons and recommendations to contribute in the future ADB operations in the agriculture sector.

view lessons »


Tajikistan: Regional Customs Modernization and Infrastructure Development Project

October 29, 2014 | Industry and Trade | Validation of Project/Program Completion Report

view lessons »


Download Report

Download Excel File

Filter Reports

Report Search & Filter Main: Tajikistan
Sending